More Progress on the studio today

This morning the beams that will support the sliding design wall doors, the baseboard and window trim and the wall material was delivered.  Then the insulation contractor came and blew in the ceiling insulation.  The wall insulation may get done later today or tomorrow.  AND the AC unit is going to be installed either today or tomorrow.   The floor is scheduled to be done at the end of the month.   The lights (there are eleven fixtures with four 4000K led bulbs in each – it’s going to be BRIGHT in there!) have been ordered,  the sliding door hardware has been ordered.  So progress is being made!